ARJ21-700 AC106 starts final assembly


ARJ21-700 AC106 was delivered to the assembly shop from the sub-assembly shop on June 28th, 2013, which was two days earlier than the schedule. Subsequently, the assembly tasks, such as laying soundproof cotton in fwd cargo compartment, ground rework of cable conductor, installation of relevant hydraulic system accessories in aft accessory compartment, pressure conduction and preparation before pressure conduction, were carried out in the assembly shop. 

Staff in the assembly shop carried out surface grinding and paint removing on inboard and outboard flap struts at the wing trailing edge of AC106 on June 28th, 2013. 

Staff laid stringer soundproof cotton in fwd cargo compartment with a height of about 1 meter on June 28th, 2013